QTS Richmond RIC5

Hyperscale data center (QTS Richmond Technology Park) Henrico County, Virginia

Proposed High ConfidenceLast updated Jul 2, 2026

10 dated events across actions, documents and updates.

  1. Jul 30, 2026Update

    Imported from the Federal Permitting Dashboard: 9 federal permitting milestones on record, lead agency Department of the Army.

  2. Jul 2, 2026Permit

    FWS determines ESA Consultation Package is Complete - Formal (Agency Action)

    Fish and Wildlife Service

  3. Jul 2, 2026Permit

    FWS determines ESA Consultation Package is Complete - Informal (Agency Action)

    Fish and Wildlife Service

  4. Jul 2, 2026Permit

    ESA Consultation Concludes (Agency Action)

    Fish and Wildlife Service

  5. Jun 9, 2026Hearing

    Publication of Public Notice (Agency Action)

    US Army Corps of Engineers - Regulatory

  6. Jun 9, 2026Environmental Review

    Determination to prepare an Environmental Assessment (EA) (Agency Action)

    US Army Corps of Engineers - Regulatory

  7. Jun 9, 2026Permit

    ESA Consultation Request Package Submitted (Agency Action)

    Fish and Wildlife Service

  8. Jun 9, 2026Permit

    Consultation initiated with SHPO/THPO (Agency Action)

    US Army Corps of Engineers - Regulatory

  9. May 27, 2026Application

    Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action)

    US Army Corps of Engineers - Regulatory

  10. Feb 13, 2026Application

    Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action)

    US Army Corps of Engineers - Regulatory